South Huron Recreation Renewal Projects

South Huron is committed to providing the best recreational opportunities that are accessible, benefit all age groups and abilities, and are affordable for the entire community. 

The following recreation renewal projects were completed in 2022/2023:

  • South Huron Recreation Centre Renewal Project
  • Stephen Township Arena Renewal Project 

South Huron Recreation Centre

South Huron Recreation Centre (SHRC) Renewal Project (Phase 1)

Project Status: Completed

 

 

At the Regular Council meeting on June 7, 2021, Council approved a renovation and retrofit of the South Huron Recreation Centre (SHRC) that will help promote and sustain multi-generational programs and services at the facility (See the news release June 9, 2021: Council Greenlights SHRC Project)

The Municipality has undertaken a review of the facility and is proposing a renovation and retrofit that will include two phases. 

The first phase, scheduled for construction in 2022, will enhance ice user experiences, increase comfort and optimal viewing for patrons, while improving the overall accessibility within the main areas of the facility.

The first phase (as approved) includes the following general parameters:

  • Dressing room addition consisting of 6 new dressing rooms, 1 officials’ room, 1 mechanical and electrical room and a connecting corridor. Note: the existing dressing rooms will be repurposed in their current footprint based on future consultation and the existing officials' room will remain unchanged to accommodate request for use.
  • New dasher board and netting system
  • Expansion of existing warm room to open concept lobby
  • Front entrance improvements
  • Incorporation of existing offices and entrances
  • Addition of two universal washrooms and viewing platform that meet AODA standards
  • Site development 

The total allocated construction budget for the above components is $4,500,000 plus HST.  

Council approved the following additional items:

Milestone Timing Status
RFP: Design and Contract Administration January 2022

Completed

Invizij Architects were awarded the Design and Contract Administration at the Regular Council meeting on January 17, 2022 (See the RFP award report: January 17, 2022) 

Design Development February/March 2022

Completed

Invizij Architects presented the Design Schematic at the March 7, 2022 Regular Council Meeting. Council motioned to accept the Design Schematic, as presented (See the staff report re: SHRC Design Approval March 7, 2022) 

Tender Preparation, Release and Award for Construction  April 2022 Tender awarded at the Regular Council meeting on June 6, 2022.    
Facility Closed to Public Access June 2022 - August 2022 Completed
Construction Period

June to October 2022 (Anticipated)

  • Completed: Zone 1 (interior work)
  • Completed: Zone 2 (addition) 
Ice Usage Resumes September 19, 2022 Completed 
Hall Rentals Resume November 1, 2022 Completed

 

 


Stephen Township Arena

Stephen Township Arena Renewal Project 

Project Status: Completed

  

 

 

At the Regular Council meeting on February 16, 2021, Council passed motion #039-2021 "That the Stephen Arena remain open and continue to operate as an arena". This work is necessary to continue operations at the Stephen Arena. This project will diversify the facility to meet future program demand. 

To support Council's motion:

It was identified that significant work is needed to continue operations at the arena, while diversifying the facility to meet future program demands. 

The capital upgrades scheduled for construction in 2022 were included in the approved budget and includes the following general parameters:

  • Rink slab replacement and components (existing sand floor to concrete)
  • Replacement of dasher boards and glass
  • Front entrance improvements to meet AODA standards

The total amount approved by Council for the Stephen Township Arena Renewal project for the above components is $2,000,000.

Council approved the following additional items:

Milestone Timing Status
Project Initiation February/March 2022

Completed

Design Development February/March 2022

Completed

Facility Closed to Public Access (as per regular ice removal schedule) Evening of April 3, 2022 Completed
Tender Preparation, Release and Award for Construction  March/April 2022

Ice Rink Floor - Tender awarded at the Regular Council meeting on Tuesday April 19, 2022

Dasherboard System - Tender awarded at the Regular Council meeting on Monday May 16, 2022

Construction Period May 2022 - August 2022 (Anticipated)

Completed - Ice Rink Floor

Completed - Dasherboard System

Completed - Accessible Front Doors

Ice Usage Resumes

October 17, 2022

Completed

New Bleacher Installation

January 2023

Completed

Contact Us

The Municipality of South Huron
322 Main Street South, P.O. Box 759
Exeter, ON N0M 1S6
Phone: 519-235-0310

Sign up to our Newsletter

Stay up to date on the city's activities, events, programs and operations by subscribing to our eNewsletters.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.